1 active project totalling 0.7 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
0.7active MW
2total filed
Queue IDProjectkVMWResourceStatus
AF1-263 Bennett-Farmingdale 2 34.5 kV 34.5 0.7 Solar Withdrawn
AG1-563 AG1-563 34.5 0.7 Solar In Service