Substation Scout

Bennett-Farmingdale 2 substation interconnection queue

1 active project totaling 0.7 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Bennett-Farmingdale 2 as the point of interconnection, all in NJ.

Target commercial operation dates as filed run from Oct 2019 to Jun 2020 (2 filings).

1active projects
0.7active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF1-263 Bennett-Farmingdale 2 34.5 kV 34.5 0.7 Solar Withdrawn Oct 2019
AG1-563 AG1-563 34.5 0.7 Solar In Service Jun 2020

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Salem County, NJ

All 114 PJM queue filings in Salem County, NJ, including 5 more substations.

Other PJM queue substations in Monmouth County, NJ

All 79 PJM queue filings in Monmouth County, NJ.