Allenwood-Larrabee 2 substation interconnection queue
1 active project totaling 1 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Allenwood-Larrabee 2 as the point of interconnection, all in Monmouth County, NJ.
Target commercial operation dates as filed run from Mar 2023 to Sep 2023 (2 filings).
1active projects
1active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI2-213 | Allenwood-Larrabee 2 34.5 kV | 34.5 | 3.1 | Solar | Withdrawn | Mar 2023 |
| AF1-260 | Lakewood-Farmingdale Road Solar Farm | 34.5 | 1 | Solar | In Service | Sep 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Monmouth County, NJ
- Howell: 1 active, 6.5 MW of 2 filed
- Hornerstown-Windsor: 1 active, 1.9 MW of 2 filed
- Bennett-Farmingdale 2: 1 active, 0.7 MW of 2 filed
- Larrabee: none active of 11 filed
- Cardiff: none active of 8 filed
- Atlantic: none active of 4 filed
- Bennett-Farmingdale: 1 active, 0 MW of 2 filed
- Englishtown: none active of 2 filed
- Fairfield: none active of 2 filed
- Great Adventure: 1 active, 0 MW of 2 filed
- Great Adventure-Great Adventure Tap: none active of 2 filed
- Larabee - Atlantic: none active of 2 filed
- Larrabee Collector Station: none active of 2 filed