3 active projects totaling 369.2 MW in the PJM queue, plus 2 with terminal status (shown grayed).

5 PJM queue filings name Salem as the point of interconnection, all in Salem County, NJ.

Target commercial operation dates as filed run from Jul 2001 to Oct 2027 (5 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: PSEG (1 filing).

3active projects
369.2active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH1-710 Salem 500kV 500 228.2 Nuclear Active Oct 2027
H17 Salem 1 & 2 500 115 Nuclear In Service Jun 2008
C07 Salem 1 & 2 500 26 Nuclear In Service Jul 2001
K01 Mannington Mills Units 1,2,3 69 8 Other Deactivated Jul 2004
X1-083 Salem 12kV 12 2.3 Solar Withdrawn May 2012

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Salem County, NJ

All 114 PJM queue filings in Salem County, NJ, including 5 more substations.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first