Substation Scout

Chambers substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).

3 PJM queue filings name Chambers as the point of interconnection, all in Salem County, NJ.

Target commercial operation dates as filed run from Jan 2008 to Jan 2028 (3 filings).

Transmission owner as filed: AEC (1 filing).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG2-451 Chambers 230 kV 230 123 Battery Withdrawn Jan 2028
AH2-132 Chambers 230kV 230 117 Battery Withdrawn Jun 2024
T135 Chambers 230kV 230 15 Coal Withdrawn Jan 2008

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Salem County, NJ

All 114 PJM queue filings in Salem County, NJ, including 5 more substations.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first