1 active project totalling 2.3 MW in the PJM queue, plus 3 with terminal status (shown greyed).

1active projects
2.3active MW
4total filed
Queue IDProjectkVMWResourceStatus
W2-019 Shemesh Solar Farm 34.5 2.3 Solar In Service
X1-077 Saylos Pond Solar Farm 34.5 0.8 Solar Withdrawn
W2-077 Wrightstown 34.5kV 34.5 0 Solar Withdrawn
W3-025 Saylors Pond Solar Farm 34.5 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.