Substation Scout

Delaware, OH interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 5 with terminal status (shown greyed).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatus
AG2-497 Tangy 138 kV 138 50 Battery Withdrawn
AG2-235 Lincoln-Berrywood 69 kV 69 30.7 Solar Withdrawn
Y1-063 Trenton 34.5kV 34.5 0 Battery Deactivated
Y1-064 Berkshire 3.4kV 34.5 0 Battery Withdrawn
Y3-097 Trent (Jug St.) 34.5kV 34.5 0 Battery Deactivated

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.