Substation Scout

Steward substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Steward as the point of interconnection, all in IL.

Target commercial operation dates as filed run from May 2019 to Jun 2021 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE1-228 Steward 138 kV 138 84 Solar Withdrawn Jun 2021
AC2-153 Steward n/r 3.8 Solar Withdrawn May 2019

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Steward (COMED, 2 mentions).

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Other PJM queue substations in Lee County, IL

All 106 PJM queue filings in Lee County, IL, including 1 more substations.

Other PJM queue substations in DeKalb County, IL

All 40 PJM queue filings in DeKalb County, IL.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first