DeKalb, IL interconnection queue
4 active projects totalling 535.7 MW in the PJM queue, plus 36 with terminal status (shown greyed).
4active projects
535.7active MW
40total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1967 | Byron - Wayne 345 kV | 345 | 198.6 | Wind | Active |
| AG1-118 | Burr Oak Solar | 138 | 180 | Solar | EP |
| AG1-119 | Wayne-Byron 345 kV | 345 | 180 | Solar | Withdrawn |
| C01-1402 | Sandwich 138kV 138 kV | 138 | 153.9 | Solar | Withdrawn |
| AG1-423 | Byron-Wayne 345 kV | 345 | 120 | Solar | Withdrawn |
| AH2-234 | W Dekalb 138 kV | 138 | 100 | Battery | Withdrawn |
| C01-1323 | Crego Rd Tap (B) - Crego Rd (B) 138 kV | 138 | 100 | Battery | Active |
| AG1-220 | West Dekalb 138 kV | 138 | 90 | Solar | Withdrawn |
| AH2-085 | Byron-Wayne 345 kV | 345 | 87.2 | Solar | Withdrawn |
| AG2-575 | Crego Rd. 138 kV | 138 | 80 | Hybrid | Withdrawn |
| AI1-170 | Glidden - Sugar Grove 138kV | 138 | 80 | Hybrid | Withdrawn |
| AI2-408 | Sugar Grove-Waterman 138kV | 138 | 72 | Solar | Withdrawn |
| AI2-409 | Wayne-Byron 345 kV | 345 | 72 | Solar | Withdrawn |
| AG1-120 | Glidden-Cherry Valley 138 kV | 138 | 71.2 | Solar | Withdrawn |
| AH1-657 | Nelson 345 kV | 345 | 60 | Solar | Withdrawn |
| AG1-127 | Red Maple Solar | 138 | 57.1 | Solar | EP |
| AH1-009 | Not reported | n/r | 54.3 | Solar | Withdrawn |
| AE2-107 | Haumesser Road 138 kV | 138 | 54 | Solar | Withdrawn |
| AF2-363 | Cherry Valley-Glidden 138 kV | 138 | 48.8 | Solar | Withdrawn |
| AD1-126 | W. DeKalb-Waterman | n/r | 48 | Solar | Withdrawn |
| AI2-417 | Wayne 345kV (CIR Increase) | 345 | 48 | Solar | Withdrawn |
| AI1-147 | Sandwich 34kV | 34 | 38.4 | Solar | Withdrawn |
| AH2-290 | Sandwich 138 kV | 138 | 34.4 | Battery | Withdrawn |
| AI2-410 | Glidden - Cherry Valley 138 kV | 138 | 28.5 | Solar | Withdrawn |
| AD1-064 | White Rock-Wayne 345kV | 345 | 26.4 | Wind | Withdrawn |
| AD2-148 | Davis Creek 345kV | 345 | 26.4 | Wind | Withdrawn |
| AD2-149 | Davis Creek 345kV | 345 | 26.4 | Wind | Withdrawn |
| AD2-150 | Davis Creek 345kV | 345 | 26.4 | Wind | Withdrawn |
| AE1-233 | West Dekalb 138 kV | 138 | 24.3 | Wind | Withdrawn |
| AI2-405 | Glidden-Waterman 138 kV (CIR Increase) | 138 | 22.8 | Solar | Withdrawn |
| AI2-411 | Glidden - Waterman 138kV (CIR Increase) | 138 | 22.8 | Solar | Withdrawn |
| AI2-420 | Crego Road 138kV (CIR Increase) | 138 | 20 | Hybrid | Withdrawn |
| AI2-403 | Glidden-Waterman 138 kV (CIR Increase) | 138 | 19.5 | Solar | Withdrawn |
| AC2-166 | Waterman 34 kV | 34 | 19 | Solar | Withdrawn |
| AH1-285 | Sandwich 138 kV | 138 | 11.2 | Solar | Withdrawn |
| AC2-149 | Glidden | n/r | 7.6 | Solar | Withdrawn |
| AC2-156 | Sandwich 34.5kV | 34.5 | 7.6 | Solar | Withdrawn |
| AC2-153 | Steward | n/r | 3.8 | Solar | Withdrawn |
| AA2-107 | Waterman 34kV | 34 | 0 | Battery | Withdrawn |
| Y2-048 | Haumesser Road | n/r | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.