Davis Creek substation interconnection queue

7 active projects totalling 725.4 MW in the PJM queue, plus 8 with terminal status (shown greyed).

7active projects
725.4active MW
15total filed
Queue IDProjectkVMWResourceStatus
AB1-091 Davis Creek 345kV 345 550 Gas Withdrawn
C01-1381 Davis Creek 345 kV 345 300 Battery Active
C01-1554 Davis Creek 138kV 138 kV 138 200 Battery Active
AD2-175 Davis Creek 345 kV 345 123 Solar Withdrawn
AH2-171 Davis Creek 345 kV 345 120 Solar Withdrawn
AI1-148 Davis Creek 138kV 138 98.4 Solar Withdrawn
AF2-095 Kankakee Solar 138 86.4 Solar EP
C01-1572 Davis Creek 138kV 138 kV 138 66 Wind Active
AD1-112 Davis Creek 138 kV 138 34 Wind Withdrawn
AD2-047 Lower Crossing Wind 138 34 Wind Suspended
AD2-148 Davis Creek 345kV 345 26.4 Wind Withdrawn
AD2-149 Davis Creek 345kV 345 26.4 Wind Withdrawn
AD2-150 Davis Creek 345kV 345 26.4 Wind Withdrawn
AD2-060 Staley Solar 138 20 Solar Engineering and Procurement
AC2-154 Staley Solar 138 19 Solar Engineering and Procurement

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.