Valley substation interconnection queue

3 active projects totaling 111.9 MW in the PJM queue, plus 7 with terminal status (shown grayed).

Target commercial operation dates as filed run from Jun 2011 to Apr 2029 (10 filings). 3 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (3 filings), Dominion (1 filing).

3active projects
111.9active MW
10total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI1-185 Valley 230 kV 230 210 Battery Withdrawn Dec 2027
AG1-195 Valley 230 kV 230 150 Hybrid Withdrawn Dec 2023
AD1-138 Valley 138 kV 138 65.8 Solar Withdrawn Dec 2020
AD2-020 Southwest Michigan Energy Center 138 61.9 Solar Engineering and Procurement Jul 2028
AE2-325 Southwest Michigan Energy Center 138 31.3 Battery Withdrawn Dec 2022
V4-016 Valley 138kV 138 26 Wind Withdrawn Nov 2014
AF1-161 Decatur Battery Storage 138 25 Battery EP Apr 2029
AG1-109 Decatur Battery Storage 138 25 Battery EP Apr 2029
AI2-340 Valley 138 kV 138 23.1 Solar Withdrawn May 2025
U4-041 Valley 13.2kV 13.2 2 Other Withdrawn Jun 2011

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Augusta County, VA

All 17 PJM queue filings in Augusta County, VA.

Other PJM queue substations in Van Buren County, MI

All 18 PJM queue filings in Van Buren County, MI.

Other PJM queue substations in Cass County, MI

All 20 PJM queue filings in Cass County, MI.

Other PJM queue substations in Adams County, PA

All 86 PJM queue filings in Adams County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first