Valley substation interconnection queue
3 active projects totalling 111.9 MW in the PJM queue, plus 7 with terminal status (shown greyed).
3active projects
111.9active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AI1-185 | Valley 230 kV | 230 | 210 | Battery | Withdrawn |
| AG1-195 | Valley 230 kV | 230 | 150 | Hybrid | Withdrawn |
| AD1-138 | Valley 138 kV | 138 | 65.8 | Solar | Withdrawn |
| AD2-020 | Southwest Michigan Energy Center | 138 | 61.9 | Solar | Engineering and Procurement |
| AE2-325 | Southwest Michigan Energy Center | 138 | 31.3 | Battery | Withdrawn |
| V4-016 | Valley 138kV | 138 | 26 | Wind | Withdrawn |
| AF1-161 | Decatur Battery Storage | 138 | 25 | Battery | EP |
| AG1-109 | Decatur Battery Storage | 138 | 25 | Battery | EP |
| AI2-340 | Valley 138 kV | 138 | 23.1 | Solar | Withdrawn |
| U4-041 | Valley 13.2kV | 13.2 | 2 | Other | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.