Substation Scout

Barterbrook-Stuarts Draft substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
AE1-084 Round Hill Solar 115 49.8 Solar Withdrawn
AG1-537 Barterbrook-Stuarts Draft 115 kV 115 32 Battery Withdrawn
AG1-325 Barterbrook-Stuarts Draft 115 kV 115 26 Hybrid Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.