Claysburg substation interconnection queue
2 active projects totalling 299.1 MW in the PJM queue, plus 1 with terminal status (shown greyed).
2active projects
299.1active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1957 | Claysburg 115 kV | 115 | 289.3 | Gas | Active |
| Q56 | Claysburg 115kV | 115 | 36 | Wind | Withdrawn |
| AF1-140 | BL-Diamond Bear Rocks | 23 | 9.8 | Solar | Under Construction |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.