Twin Branch - Argenta substation interconnection queue

2 active projects totaling 384 MW in the PJM queue.

2 PJM queue filings name Twin Branch - Argenta as the point of interconnection, all in Cass County, MI.

Target commercial operation date as filed: Dec 2030 (2 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (2 filings).

2active projects
384active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1409 Twin Branch - Argenta 345 kV 345 200 Battery Active Dec 2030
C01-1203 Twin Branch - Argenta 345 kV 345 184 Solar Active Dec 2030

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Cass County, MI

All 20 PJM queue filings in Cass County, MI.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first