Twin Branch - Argenta substation interconnection queue
2 active projects totaling 384 MW in the PJM queue.
2 PJM queue filings name Twin Branch - Argenta as the point of interconnection, all in Cass County, MI.
Target commercial operation date as filed: Dec 2030 (2 filings). 2 active filings target a date after November 27, 2026.
Transmission owner as filed: AEP (2 filings).
2active projects
384active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1409 | Twin Branch - Argenta 345 kV | 345 | 200 | Battery | Active | Dec 2030 |
| C01-1203 | Twin Branch - Argenta 345 kV | 345 | 184 | Solar | Active | Dec 2030 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Cass County, MI
- Cook-East Elkhart: 2 active, 1,085 MW of 2 filed
- Valley: 3 active, 111.9 MW of 10 filed
- Kenzie Creek-Stone Lake: 1 active, 100 MW of 2 filed
- Kenzie Creek-Colby: none active of 3 filed
- Brody: none active of 2 filed
Site Scanner