Decatur Battery Storage

PJM queue ID AF1-161

Decatur Battery Storage (AF1-161) is listed in the PJM interconnection queue as a 25 MW battery project in Van Buren County, MI. The filing names Valley as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of April 30, 2029.

Queue IDAF1-161
Project nameDecatur Battery Storage
Status (as published)EP
SubstationValley
Point of interconnectionValley 138 kV
CountyVan Buren
StateMI
Voltage138 kV
Capacity25 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-04-30
Source datasetcycle

Same substation and county

Valley substation: 10 requests in the PJM queue, 3 active totaling 111.9 MW.

Queue IDProjectMWResourceStatus
AD2-020Southwest Michigan Energy Center61.9SolarEngineering and Procurement
AG1-109Decatur Battery Storage25BatteryEP
AI1-185Valley 230 kV210BatteryWithdrawn
AG1-195Valley 230 kV150HybridWithdrawn
AD1-138Valley 138 kV65.8SolarWithdrawn
AE2-325Southwest Michigan Energy Center31.3BatteryWithdrawn
V4-016Valley 138kV26WindWithdrawn
AI2-340Valley 138 kV23.1SolarWithdrawn
U4-041Valley 13.2kV2OtherWithdrawn

Van Buren, MI: 18 requests in the PJM queue, 6 active totaling 1,221 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperDecatur Storage LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
MW energy50.0
MW capacity25.0
MFO50.0
Submitted date9/20/2019
Last updated4/29/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.