Van Buren, MI interconnection queue
7 active projects totalling 1,344.9 MW in the PJM queue, plus 11 with terminal status (shown greyed).
7active projects
1,344.9active MW
18total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| T94 | Cook-Palesades 345kV | 345 | 1,035 | Gas | In Service |
| AD2-075 | Covert Generating Facility | 345 | 145 | Gas | Withdrawn |
| AH1-272 | Argenta - Twin Branch 345 kV | 345 | 123.9 | Solar | Active |
| AH2-149 | Stinger - Valley 138 kV | 138 | 120 | Hybrid | Withdrawn |
| AI2-358 | Argenta - Twin Branch 345 kV | 345 | 70 | Solar | Withdrawn |
| AD1-138 | Valley 138 kV | 138 | 65.8 | Solar | Withdrawn |
| AD2-020 | Southwest Michigan Energy Center | 138 | 61.9 | Solar | Engineering and Procurement |
| AH1-310 | Colby - Valley 138 kV | 138 | 60 | Solar | Withdrawn |
| AF1-084 | Murch Solar | 69 | 54.1 | Solar | Under Construction |
| AG2-130 | Colby Tap-Valley 138 kV | 138 | 37.2 | Hybrid | Withdrawn |
| AE2-325 | Southwest Michigan Energy Center | 138 | 31.3 | Battery | Withdrawn |
| AI2-193 | East Hartford - Murch 69 kV | 69 | 28.4 | Solar | Withdrawn |
| AF1-161 | Decatur Battery Storage | 138 | 25 | Battery | EP |
| AG1-109 | Decatur Battery Storage | 138 | 25 | Battery | EP |
| AI2-340 | Valley 138 kV | 138 | 23.1 | Solar | Withdrawn |
| AC1-072 | Covert Generating Facility | 345 | 20 | Gas | In Service |
| AG2-131 | Almena-Valley 69 kV | 69 | 20 | Solar | Withdrawn |
| AG2-132 | Hartford-South Haven 69 kV | 69 | 7.5 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.