Southwest Michigan Energy Center
PJM queue ID AD2-020
Southwest Michigan Energy Center (AD2-020) is listed in the PJM interconnection queue as a 61.9 MW solar project in Van Buren County, MI. The filing names Valley as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of July 31, 2028.
| Queue ID | AD2-020 |
|---|---|
| Project name | Southwest Michigan Energy Center |
| Status (as published) | Engineering and Procurement |
| Substation | Valley |
| Point of interconnection | Valley 138 kV |
| County | Van Buren |
| State | MI |
| Voltage | 138 kV |
| Capacity | 61.9 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-07-31 |
| Source dataset | serial |
Same substation and county
Valley substation: 10 requests in the PJM queue, 3 active totaling 111.9 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF1-161 | Decatur Battery Storage | 25 | Battery | EP |
| AG1-109 | Decatur Battery Storage | 25 | Battery | EP |
| AI1-185 | Valley 230 kV | 210 | Battery | Withdrawn |
| AG1-195 | Valley 230 kV | 150 | Hybrid | Withdrawn |
| AD1-138 | Valley 138 kV | 65.8 | Solar | Withdrawn |
| AE2-325 | Southwest Michigan Energy Center | 31.3 | Battery | Withdrawn |
| V4-016 | Valley 138kV | 26 | Wind | Withdrawn |
| AI2-340 | Valley 138 kV | 23.1 | Solar | Withdrawn |
| U4-041 | Valley 13.2kV | 2 | Other | Withdrawn |
Van Buren, MI: 18 requests in the PJM queue, 6 active totaling 1,221 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 100 |
| MW capacity | 61.9 |
| MFO | 100 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.