Southwest Michigan Energy Center

PJM queue ID AD2-020

Queue IDAD2-020
Project nameSouthwest Michigan Energy Center
Status (as published)Engineering and Procurement
SubstationValley
Point of interconnectionValley 138 kV
CountyVan Buren
StateMI
Voltage138 kV
Capacity61.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-07-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity61.9
Mfo100