Adams, PA interconnection queue
14 active projects totalling 2,282.3 MW in the PJM queue, plus 72 with terminal status (shown greyed).
14active projects
2,282.3active MW
86total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AB1-153 | Hunterstown 500kV | 500 | 985.1 | Gas | Withdrawn |
| C01-1881 | Hunterstown 230 kV | 230 | 931.1 | Gas | Active |
| A36 | Hunterstown | 500 | 830 | Gas | In Service |
| A60 | Hunterstown 500 kV | 500 | 679 | Gas | Withdrawn |
| C01-1398 | Hunterstown 500 kV | 500 | 366.8 | Gas | Active |
| Y2-002 | Not reported | n/r | 350 | Gas | Withdrawn |
| AH2-235 | Orrtana 115 kV | 115 | 125 | Battery | Withdrawn |
| AH2-230 | Gardners 115 kV | 115 | 75 | Battery | Withdrawn |
| AH1-476 | Hunterstown-Texas Eastern Tap 115 kV II | 115 | 73 | Solar | Withdrawn |
| AB2-071 | Hunterstown-Lincoln 115kV | 115 | 68 | Solar | Withdrawn |
| Y2-016 | Not reported | n/r | 68 | Wind | Withdrawn |
| AD1-020 | Adams Solar LLC | 115 | 53.6 | Solar | In Service |
| AE1-253 | Tidd-Collier 345kV | 345 | 50 | Not reported | Withdrawn |
| AE2-345 | Granite Hill Solar | 115 | 42 | Solar | Suspended |
| AE1-131 | Gardners-Hunterstown 115 kV | 115 | 39 | Solar | Withdrawn |
| AE1-139 | Hunterstown 115 kV | 115 | 39 | Solar | Withdrawn |
| AE2-192 | Orrtanna 115 kV | 115 | 39 | Solar | Withdrawn |
| W4-022 | Hunterstown 230kV | 230 | 38 | Solar | Withdrawn |
| X3-022 | Hunterstown-Jackson 138kV | 138 | 38 | Solar | Withdrawn |
| AE2-279 | Oxford 115 kV | 115 | 26.4 | Solar | Withdrawn |
| AF2-439 | Roxbury-Carlisle 115 kV | 115 | 26 | Solar | Withdrawn |
| AG1-482 | Hamilton Solar and BESS | 115 | 20 | Hybrid | Withdrawn |
| AH1-708 | Not reported | n/r | 20 | Gas | Withdrawn |
| Y3-114 | Not reported | n/r | 19.9 | Gas | Withdrawn |
| AF1-309 | North Hanover 115 kV | 115 | 19.2 | Solar | Withdrawn |
| AG1-486 | Orrtanna | 115 | 15 | Battery | Withdrawn |
| AC1-048 | Brookview Solar I | 115 | 13.3 | Solar | Withdrawn |
| AE1-138 | Hamilton 115 kV | 115 | 13.2 | Solar | Withdrawn |
| AE1-187 | North Lebanon- Cleona 69 kV | 69 | 12.6 | Solar | Withdrawn |
| AE2-116 | Midland 23 kV III | 23 | 12 | Solar | Withdrawn |
| AE2-119 | Shawville-Phillipsburg 34.5 kV | 34.5 | 12 | Solar | Withdrawn |
| AF1-242 | Wilcox-Paper City 46 kV | 46 | 12 | Solar | Withdrawn |
| AF2-340 | Not reported | n/r | 12 | Solar | Withdrawn |
| AF2-417 | WA-Cochecton 2 | 69 | 12 | Solar | Engineering and Procurement |
| AF2-421 | Club Ford Energy Center | n/r | 12 | Solar | Engineering and Procurement |
| AF2-425 | Shamrock Energy Center | 69 | 12 | Solar | Under Construction |
| AH1-049 | Erie East – Union City Ckt 00234-31 34.5 kV | 34.5 | 12 | Solar | Withdrawn |
| AE2-009 | Nottingham-Peach Bottom Tap 230 kV line | 230 | 11 | Not reported | Withdrawn |
| AF1-140 | BL-Diamond Bear Rocks | 23 | 9.8 | Solar | Under Construction |
| AF1-024 | Freeland Municipal Authority | n/r | 9.7 | Solar | Withdrawn |
| AF1-241 | Watson 12.47 kV | 12.5 | 9 | Solar | Withdrawn |
| AI1-144 | Gardners 13.2 kV III | 13.2 | 8 | Hybrid | Withdrawn |
| AI1-193 | Lincoln 13.2 kV II | 13.2 | 8 | Hybrid | Withdrawn |
| AI1-194 | Orrtanna 13.2 kV III | 13.2 | 8 | Hybrid | Withdrawn |
| AI1-195 | Orrtanna 13.2 kV IV | 13.2 | 8 | Hybrid | Withdrawn |
| AI1-197 | Gardners 13.2 kV | 13.2 | 8 | Hybrid | Withdrawn |
| AC2-053 | Brookview Solar I | 115 | 7.6 | Solar | Withdrawn |
| AE1-006 | Brookview Solar I | 115 | 7.6 | Solar | Withdrawn |
| V3-031 | Germantown | n/r | 7.6 | Solar | Withdrawn |
| W1-075 | Hunterstown 115kV | 115 | 7.6 | Solar | Withdrawn |
| W2-092 | Hunterstown 115kV II | 115 | 7.6 | Solar | Withdrawn |
| W2-093 | Hunterstown 115kV III | 115 | 7.6 | Solar | Withdrawn |
| W2-098 | Hunterstown 115kV IV | 115 | 7.6 | Solar | Withdrawn |
| W3-064 | Hunterstown 115kV V | 115 | 7.6 | Solar | Withdrawn |
| W3-067 | Gardners-Hunterstown 115kV | 115 | 7.6 | Solar | Withdrawn |
| AG2-648 | Germantown 13.2 kV | 13.2 | 6.2 | Solar | Withdrawn |
| AI1-198 | Gardners 13.2 kV II | 13.2 | 5.8 | Hybrid | Withdrawn |
| W3-168 | Germantown 13.2 kV | 13.2 | 5.7 | Solar | Withdrawn |
| AG1-294 | Not reported | n/r | 5 | Solar | Withdrawn |
| AI2-292 | Hunterstown-Texas Eastern Tap 115 kV III | 115 | 4.9 | Solar | Withdrawn |
| W3-169 | North Hanover 12.5kV | 12.5 | 4.6 | Solar | Withdrawn |
| AD2-061 | Spring Run 23 kV | 23 | 4.5 | Solar | Withdrawn |
| AF1-182 | Shawville Generating Station | 230 | 4 | Gas | In Service |
| AF1-193 | Hunterstown CT Facility | 115 | 4 | Gas | In Service |
| AG1-332 | Oxford 13.2 kV | 13.2 | 3.7 | Solar | Withdrawn |
| AF1-181 | Shawville Generating Station | 230 | 3 | Gas | In Service |
| AG2-027 | Orrtanna 13.2 kV | 13.2 | 2.1 | Solar | Withdrawn |
| AG2-028 | Lincoln 13.2 kV | 13.2 | 2.1 | Solar | Withdrawn |
| AG2-139 | Lincoln 771-4 13.2 kV | 13.2 | 2 | Solar | Withdrawn |
| U4-040 | Lincoln 13.2kV | 13.2 | 2 | Gas | Withdrawn |
| U4-041 | Valley 13.2kV | 13.2 | 2 | Other | Withdrawn |
| AF2-102 | PA Adams Ramsburg | 13.2 | 1.8 | Solar | Withdrawn |
| AF2-175 | Straban 13.2 kV | 13.2 | 1.8 | Solar | Withdrawn |
| W2-094 | Lincoln Solar Farm | 13.2 | 1.1 | Solar | Withdrawn |
| AF1-183 | Shawville Generating Station | 230 | 1 | Gas | In Service |
| AF1-188 | Orrtanna Station Unit C1 | 115 | 1 | Other | In Service |
| AF2-268 | AD-Chambersburg | 13.2 | 0 | Hybrid | Withdrawn |
| AG2-141 | Wylie Ridge-Toronto 345 kV | 345 | 0 | Not reported | Withdrawn |
| AG2-390 | Upper Providence 34.5 kV | 34.5 | 0 | Hybrid | Withdrawn |
| AG2-399 | Harrisville Jct - All Min 25 kV | 25 | 0 | Solar | Withdrawn |
| AG2-493 | Phillipsburg Bus II 34.5 kV | 34.5 | 0 | Solar | Withdrawn |
| AG2-495 | Phillipsburg Bus I 34.5 kV | 34.5 | 0 | Solar | Withdrawn |
| AH1-137 | Not reported | n/r | 0 | Solar | Withdrawn |
| AH1-284 | West Willow 12 kV | 12 | 0 | Solar | Withdrawn |
| C01-1748 | Texas Eastern 115 kV | 115 | 0 | Solar | Withdrawn |
| P29 | Hunterstown 500/230kV | 230 | 0 | Not reported | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.