Gray Bark

Named in 2 PJM planning documents for 1 project, from January 7, 2025 to October 8, 2025.

Newdescribed as
DOMzone
230kVkV as printed
2mentions

Described as new: “new substation (Gray Bark)” — source, page 9

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gray Bark 230kV Delivery - DEV
DOM-2024-0019 · s3676
Engineering $20M Substation, $20M Transmission Lines Q3 2027 300.0 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 30
Gray Bark 230kV Delivery - DEV “new substation (Gray Bark)”
230kV
2025-01-07 TEAC
Item 10 - Dominion Supplemental Projects p. 9
Gray Bark 230kV Delivery - DEV “new substation (Gray Bark)”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.