Saltwood

Named in 2 PJM planning documents for 3 projects, from January 7, 2025 to October 8, 2025.

Newdescribed as
DOMzone
230kVkV as printed
6mentions

Described as new: “new substation (Saltwood)” — source, page 5

Also printed as: Saltwood substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gray Bark 230kV Delivery - DEV
DOM-2024-0019 · s3676
Engineering $20M Substation, $20M Transmission Lines Q3 2027 300.0 MW 2025-10-08
TEAC
Saltwood 230kV Delivery - DEV
DOM-2024-0020 · s3674
Engineering $20M Substation, $20M Transmission Line Q3 2027 300.0 MW 2025-10-08
TEAC
Bunker 230kV Delivery - DEV
DOM-2024-0040 · s3675
Engineering $15M Substation, $6M Transmission Line Q4 2027 104.0 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 26
Saltwood 230kV Delivery - DEV “new substation (Saltwood)”
230kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 29
Bunker 230kV Delivery - DEV “proposed Saltwood substation”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 31
Gray Bark 230kV Delivery - DEV “proposed Saltwood substation”
230kV
2025-01-07 TEAC
Item 10 - Dominion Supplemental Projects p. 10
Gray Bark 230kV Delivery - DEV No role wording
230kV
2025-01-07 TEAC
Item 10 - Dominion Supplemental Projects p. 5
Saltwood 230kV Delivery - DEV “new substation (Saltwood)”
230kV
2025-01-07 TEAC
Item 10 - Dominion Supplemental Projects p. 8
Bunker 230kV Delivery - DEV No role wording
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.