Allied
Named in 4 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.
Existingdescribed as
DOMzone
—kV as printed
4mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Bermuda Hundred 230kV Delivery - DEV DOM-2019-0021 · s3509.1 |
Engineering | $15.0 M | Q4 2026 | 100 MW | 2024-10-08 TEAC |
| Do No Harm Analysis DOM-2022-0062-DNH · s3862.2, s3862.3 |
Conceptual | Not printed | Q4 2031 | Not printed | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $101.7M → $15.0 M | 2026-10-06 | Not reported |
| Cost estimate | $15.0 M → $92.7M | 2024-10-08 | 2024-12-03 |
| Cost estimate prior value printed on the same page |
$92.7M → $95.1M | 2026-01-06 | 2026-01-06 |
| Cost estimate | $92.7M → $95.1M | 2025-10-08 | 2026-01-06 |
| Cost estimate prior value printed on the same page |
$95.1M → 101.7M | 2026-07-07 | 2026-07-07 |
| Cost estimate | $95.1M → 101.7M | 2026-01-06 | 2026-07-07 |
| Cost estimate prior value printed on the same page |
$92.7M → $101.7M | 2026-10-06 | 2026-10-06 |
| In-service date | Q4 2030 → Q4 2026 | 2026-10-06 | Not reported |
| In-service date | Q4 2026 → Q4 2028 | 2024-10-08 | 2024-12-03 |
| In-service date | Q4 2028 → Q4 2030 | 2026-01-06 | 2026-07-07 |
| Status | conceptual (Conceptual) → engineering (Engineering) | 2026-10-06 | Not reported |
| Status | engineering (Engineering) → conceptual (Conceptual) | 2026-01-06 | 2026-07-07 |
| Substations named | ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ALLIED; BERMUDA HUNDRED; ICI | 2026-10-06 | Not reported |
| Substations named | ALLIED; BERMUDA HUNDRED; ICI → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS | 2024-10-08 | 2024-12-03 |
| Substations named | BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS → ENON; MEADOWVILLE; SYCAMORE SPRINGS | 2024-12-03 | 2025-10-08 |
| Substations named | ENON; MEADOWVILLE; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS | 2025-10-08 | 2026-01-06 |
| Substations named | BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS | 2026-01-06 | 2026-07-07 |
| Substations named | BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS | 2026-07-07 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 109 |
Do No Harm Analysis | No role wording |
| 2026-09-08* | SRRTEP Southern Dominion p. 160 |
Bermuda Hundred 230kV Delivery - DEV | “230kV Line 2050 (ICI to Allied)” |
| 2026-07-07 | TEAC Item 14 - DOM Supplemental Projects p. 5 |
Do No Harm Analysis | No role wording |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 160 |
Bermuda Hundred 230kV Delivery - DEV | No role wording |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.