Susquehanna substation interconnection queue

4 active projects totalling 68 MW in the PJM queue, plus 9 with terminal status (shown greyed).

4active projects
68active MW
13total filed
Queue IDProjectkVMWResourceStatus
R94 Susquehanna n/r 940 Coal Withdrawn
R95 Susquehanna n/r 940 Coal Withdrawn
R01 Susquehanna n/r 800 Nuclear Withdrawn
R02 Susquehanna n/r 800 Nuclear Withdrawn
U4-005 Susquehanna n/r 640 Gas Withdrawn
B42 Susquehanna 230kV 230 500 Gas Withdrawn
A09 Susquehanna #1 230 35 Nuclear In Service
A08 Susquehanna #1 230 15 Nuclear In Service
H02 Susquehanna #1 230 9 Nuclear In Service
H03 Susquehanna #2 500 9 Nuclear In Service
H01 Susquehanna 500kV 500 2 Nuclear Withdrawn
X3-056 Susquehanna 230kV 230 0 Nuclear Withdrawn
X3-057 Susquehanna 230kV 230 0 Nuclear Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.