Substation Scout

Susquehanna-Lackawanna substation interconnection queue

3 active projects totalling 1,045 MW in the PJM queue, plus 1 with terminal status (shown greyed).

3active projects
1,045active MW
4total filed
Queue IDProjectkVMWResourceStatus
Z2-046 Freedom Generation Plant 500 900 Gas In Service
AC1-081 Susquehanna-Lackawanna 500kV 500 180 Gas Withdrawn
AA1-066 Freedom Generation Plant 500 80 Gas In Service
AC2-092 Freedom Generation Plant 500 65 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.