West Berwick substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
Target commercial operation dates as filed run from Dec 2022 to Jun 2024 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG1-204 | West Berwick 12.47 kV | 12.5 | 6.5 | Solar | Withdrawn | Dec 2022 |
| AH1-496 | West Berwick 12 kV | 12 | 6.4 | Solar | Withdrawn | Jun 2024 |
| AG2-395 | CO-Ridge | 12 | 0 | Hybrid | Withdrawn | Apr 2024 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Columbia County, PA
- Susquehanna: 4 active, 68 MW of 13 filed
- Columbia-Geisinger Tap #1: 2 active, 24 MW of 2 filed
- Rohrsburg: none active of 3 filed
- Columbia-West Bloomsburg II: none active of 2 filed
- West Boyertown: none active of 2 filed
Other PJM queue substations in City of Lynchburg, VA
- Reusens: 1 active, 4 MW of 3 filed
- Rohrsburg: none active of 3 filed
- Trexlertown: none active of 2 filed