Substation Scout

Wright substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
K03 Wright 69kV 69 39.6 Wind Withdrawn
E11 Wright 69kV 69 16.9 Gas Withdrawn
E15 Wright 69kV 69 16.9 Gas Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.