Derry Tap-Derry Bus substation interconnection queue
1 active project totaling 8.4 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Derry Tap-Derry Bus as the point of interconnection, all in PA.
Target commercial operation dates as filed run from May 2024 to Apr 2026 (2 filings).
1active projects
8.4active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE2-059 | Cottontail Solar 4 aka East Chilli Solar | 69 | 8.4 | Solar | In Service | May 2024 |
| AE2-084 | Cottontail Solar 3 | 69 | 8.4 | Solar | Withdrawn | Apr 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Northumberland County, PA
- Hamilton: 2 active, 500 MW of 5 filed
- Milton: 1 active, 43.5 MW of 4 filed
- Derry Tap-Derry Bus III: 1 active, 4.1 MW of 2 filed
- TBD: none active of 20 filed
- Watson: none active of 4 filed
- Sunbury-Dalmatia: none active of 2 filed
- Sunbury-Milton: none active of 2 filed
Other PJM queue substations in Montour County, PA
- Montour: 2 active, 581 MW of 14 filed
- Susquehanna: 4 active, 68 MW of 13 filed
- Montour #1: 2 active, 16 MW of 2 filed
- Derry Tap-Derry Bus III: 1 active, 4.1 MW of 2 filed
- Derry: none active of 2 filed