Jenkins-Harwood #2 substation interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| O28 | Penobscot Mountain WF | 69 | 10.2 | Wind | Withdrawn |
| L07 | Mountain Top | 69 | 8.6 | Wind | Withdrawn |
| M02 | Mountain Top | n/r | 8.1 | Wind | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.