Morrisville substation interconnection queue
1 active project totalling 400 MW in the PJM queue, plus 11 with terminal status (shown greyed).
1active projects
400active MW
12total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| R77 | Morrisville 500kV | 500 | 600 | Gas | Withdrawn |
| S52 | Morrisville 500kV | 500 | 600 | Gas | Withdrawn |
| C01-1376 | Morrisville 230 kV | 230 | 400 | Battery | Active |
| AD2-190 | Morrisville 230 kV | 230 | 111.8 | Solar | Withdrawn |
| AE1-022 | Morrisville 230 kV | 230 | 111.8 | Solar | Withdrawn |
| AE1-044 | Fitch Solar | 230 | 111.8 | Solar | Withdrawn |
| AH1-086 | Summersweet Energy Center, LLC | 230 | 90 | Battery | Withdrawn |
| AD2-032 | Morrisville 230 kV | 230 | 83.8 | Solar | Withdrawn |
| AG2-644 | Morrisville 230 kV | 230 | 80 | Battery | Withdrawn |
| AH1-087 | Summersweet Energy Center, LLC | 230 | 20 | Battery | Withdrawn |
| AH1-088 | Summersweet Energy Center, LLC | 230 | 20 | Battery | Withdrawn |
| AH1-089 | Summersweet Energy Center, LLC | 230 | 20 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.