Suffolk substation interconnection queue
4 active projects totalling 120.8 MW in the PJM queue, plus 10 with terminal status (shown greyed).
4active projects
120.8active MW
14total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AI1-102 | Suffolk 115 kV | 115 | 100 | Battery | Withdrawn |
| C01-1685 | Suffolk 230 kV | 230 | 74.5 | Battery | Active |
| AH2-107 | Suffolk 115 kV | 115 | 69 | Battery | Withdrawn |
| AG1-518 | Suffolk 230 kV | 230 | 50 | Hybrid | Withdrawn |
| C01-1686 | Suffolk 230 kV | 230 | 24.5 | Battery | Active |
| X1-053 | Suffolk 34.5kV | 34.5 | 20 | Gas | Withdrawn |
| AE2-104 | Switchgrass Solar 1 | 115 | 18.9 | Solar | Withdrawn |
| AE2-225 | Hosier Road Solar | 34 | 12 | Solar | Withdrawn |
| AF2-043 | Pleasant Hill Solar | 34.5 | 12 | Solar | In Service |
| AF1-032 | Stratford Solar Center | 34.5 | 9.8 | Solar | In Service |
| AE2-229 | Hosier Road Solar II | 34 | 9 | Solar | Withdrawn |
| Y2-066 | Suffolk Landfill Units 1-10 | 34.5 | 9 | Gas | Withdrawn |
| AF1-016 | Suffolk 115 kV | 115 | 7.7 | Solar | Withdrawn |
| AF2-110 | Switchgrass Solar 1 | 115 | 7.7 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.