Wattsville substation interconnection queue
1 active project totaling 9 MW in the PJM queue, plus 2 with terminal status (shown grayed).
3 PJM queue filings name Wattsville as the point of interconnection, all in Accomack County, VA.
Target commercial operation dates as filed run from Jun 2021 to Apr 2026 (3 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-061 | Scout Energy Storage | 69 | 40 | Battery | Withdrawn | Jun 2021 |
| AF2-060 | Scout Storage I | 12 | 9 | Battery | Suspended | Apr 2026 |
| AE1-167 | Wattsville 12 kV | 12 | 6 | Solar | Withdrawn | Jun 2021 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “Wattsville” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Wattsville Substation: Expansion Tracker, PJM planning: Zone not identified state not printed
Other PJM queue substations in Accomack County, VA
- Morrisville: 1 active, 400 MW of 12 filed
- Suffolk: 4 active, 120.8 MW of 14 filed
- Carson-Rogers Rd: 1 active, 67.7 MW of 5 filed
- Oak Hall: 8 active, 47.2 MW of 10 filed
- Tasley: 2 active, 16.1 MW of 9 filed
- Northern Neck: 3 active, 8.4 MW of 6 filed
- Tasley-Kellam: none active of 4 filed
- Birchwood: none active of 3 filed
- Sowego: none active of 3 filed
- Bremo-Kidds Store: none active of 2 filed
- Briery DP-Clover: none active of 2 filed
- Carson – Rogers Road: none active of 2 filed
- New Church: none active of 2 filed