Wattsville substation interconnection queue
1 active project totalling 9 MW in the PJM queue, plus 2 with terminal status (shown greyed).
1active projects
9active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AF2-061 | Scout Energy Storage | 69 | 40 | Battery | Withdrawn |
| AF2-060 | Scout Storage I | 12 | 9 | Battery | Suspended |
| AE1-167 | Wattsville 12 kV | 12 | 6 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.