Oak Hall substation interconnection queue
8 active projects totalling 47.2 MW in the PJM queue, plus 2 with terminal status (shown greyed).
8active projects
47.2active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| W3-054A | Oak Hall 138kV | 138 | 12.4 | Wind | Withdrawn |
| W1-003 | Oak Hall Project A | n/r | 7.6 | Solar | In Service |
| W1-004 | Oak Hall Project B | n/r | 7.6 | Solar | In Service |
| W1-005 | Oak Hall Project C | n/r | 7.6 | Solar | In Service |
| W1-006 | Oak Hall Project D | n/r | 7.6 | Solar | In Service |
| W1-007 | Oak Hall | n/r | 7.6 | Solar | Withdrawn |
| Z1-100 | Oak Hal lProject A | n/r | 4.2 | Solar | In Service |
| Z1-101 | Oak Hall Project B | n/r | 4.2 | Solar | In Service |
| Z1-102 | Oak Hall Project C | n/r | 4.2 | Solar | In Service |
| Z1-103 | Oak Hall | n/r | 4.2 | Solar | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.