Front Royal substation interconnection queue
3 active projects totalling 1,350 MW in the PJM queue.
3active projects
1,350active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| V2-030 | Warren County | 500 | 875 | Gas | In Service |
| V4-018 | Warren County | 500 | 415 | Gas | In Service |
| W3-047 | Warren County | 500 | 60 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.