Morgantown substation interconnection queue

2 active projects totalling 270 MW in the PJM queue, plus 8 with terminal status (shown greyed).

2active projects
270active MW
10total filed
Queue IDProjectkVMWResourceStatus
AI2-457 Morgantown 230 kV 230 1,122 Battery Withdrawn
C01-2107 Morgantown 230 KV 230 kV 230 1,122 Battery Withdrawn
B50 Morgantown 69kV 69 500 Gas Withdrawn
C01-1943 Morgantown 230 kV 230 190 Battery Active
AG2-301 Morgantown 230 kV 230 150 Battery Withdrawn
B02 Morgantown Units 1 & 2 n/r 80 Gas In Service
T171 Newburg High Efficiency Flywheel 69 20 Battery Withdrawn
V4-012 Morgantown n/r 4.8 Gas Withdrawn
L03 Morgantown LF n/r 0.8 Gas Withdrawn
W4-070 Morgantown n/r 0.8 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.