South Reading substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
B21 South Reading 500kV 500 925 Gas Withdrawn
Q73 Evergreen Community Power 69 16 Other Deactivated
R57 Evergreen Community Power 69 9 Other Deactivated

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.