Washington, PA interconnection queue

8 active projects totalling 2,424.4 MW in the PJM queue, plus 19 with terminal status (shown greyed).

8active projects
2,424.4active MW
27total filed
Queue IDProjectkVMWResourceStatus
C01-1440 Collier - Clinton 345 kV 345 1,425 Gas Active
AB1-069 Beech Hollow Energy Center 500 950 Gas Withdrawn
C01-1630 Wylie Ridge - Tidd 345 kV 345 750 Gas Active
Z2-064 Smith-N. Fayette 138kV 138 600 Gas Withdrawn
Y3-042 Elrama 69kV 69 460 Gas Withdrawn
N40 Champion 345kV 345 300 Coal Withdrawn
C01-1174 Vanceville 138 kV 138 200 Battery Active
M26 Beech Hollow n/r 150 Gas Withdrawn
AA2-043 Smith-N. Fayette 138kV 138 99 Gas Withdrawn
AE1-080 Wylie Ridge 500 kV 500 80 Gas Withdrawn
AH1-545 Cornerstone Solar 345 20 Solar Active
T156 Champion n/r 20 Coal Withdrawn
AA2-080 Ellsworth-Eppler Junction 25kV 25 19.9 Gas Withdrawn
AA2-134 Andrew Shaft-84 Junction 25kV 25 19.9 Gas Withdrawn
Y3-109 Red Glen Generator 25 19.9 Gas Withdrawn
Z2-105 Ten Mile Generation Facility 25 19.9 Gas Withdrawn
Z2-106 Amity Generation Facility 25 19.9 Gas Withdrawn
AG1-385 Motion-Ridgeway 46 kV 46 15.4 Solar Withdrawn
AG1-386 Smith-Francis Junction 25 kV 25 15.4 Solar In Service
N37 Windsor 138kV 138 10 Wind Withdrawn
P34 Washington Landfill n/r 6.4 Gas In Service
AC2-168 Gaucho Solar 23 4.4 Solar In Service
AD1-135 Gaucho Solar 23 3.2 Solar In Service
AB1-078 Wilson 34.5kV 34.5 0 Battery Withdrawn
AB2-046 Charleroi 12kV 12 0 Gas Withdrawn
AG1-309 Byron 345 kV 345 0 Not reported Withdrawn
X3-034 Hunterstown-Jackson 130kV 130 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.