Suffolk, VA interconnection queue
5 active projects totalling 329 MW in the PJM queue, plus 2 with terminal status (shown greyed).
5active projects
329active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1405 | Suffolk - Nucor Tap 230 kV | 230 | 120 | Battery | Withdrawn |
| C01-2016 | Suffolk - Sunbury 230 kV | 230 | 120 | Hybrid | Active |
| C01-1303 | Suffolk - Nucor Tap 230 kV | 230 | 110.4 | Solar | Withdrawn |
| C01-1685 | Suffolk 230 kV | 230 | 74.5 | Battery | Active |
| C01-1304 | Copeland DP - Holland 115 kV | 115 | 60 | Solar | Active |
| C01-1307 | Copeland DP - Holland 115 kV | 115 | 50 | Battery | Active |
| C01-1686 | Suffolk 230 kV | 230 | 24.5 | Battery | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.