Kings Fork substation interconnection queue

1 active project totaling 9.7 MW in the PJM queue, plus 3 with terminal status (shown grayed).

4 PJM queue filings name Kings Fork as the point of interconnection, all in City of Suffolk, VA.

Target commercial operation dates as filed run from Jun 2011 to Dec 2021 (4 filings).

1active projects
9.7active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
U2-031 Kings Fork 34.5kV 34.5 24.8 Gas Withdrawn Jun 2011
AD2-215 Godwin Blvd Solar 34.5 9.8 Solar Withdrawn Dec 2021
AD1-144 TWE Myrtle Solar Project 34.5 9.7 Solar In Service Jun 2020
AA2-040 Kings Fork 34.5kV 34.5 0 Other Withdrawn Aug 2015

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Kings Fork” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in City of Suffolk, VA

All 28 PJM queue filings in City of Suffolk, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first