Substation Scout

Suffolk 230 kV

PJM queue ID C01-1685

Queue IDC01-1685
Project nameSuffolk 230 kV
Status (as published)Active
SubstationSuffolk
Point of interconnectionSuffolk 230 kV
CountySuffolk
StateVA
Voltage230 kV
Capacity74.5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2031-12-31
Source datasetcycle

Additional filed fields

DeveloperSwitchgrass Solar I, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy149.0
Mw Capacity74.5
Mfo149.0
Submitted Date4/24/2026
Last Updated6/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.