Substation Scout

Surry-Skiffes Creek substation interconnection queue

1 active project totalling 650 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
650active MW
2total filed
Queue IDProjectkVMWResourceStatus
AH1-716 Surry-Skiffes Creek 500kV 500 650 Battery Active
AH1-726 Surry-Skiffes Creek 500kV 500 600 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.