Heritage - Wake substation interconnection queue
5 active projects totaling 341.6 MW in the PJM queue, plus 2 with terminal status (shown grayed).
Target commercial operation dates as filed run from Dec 2025 to Dec 2030 (7 filings). 5 active filings target a date after November 27, 2026.
Transmission owner as filed: Dominion (6 filings).
5active projects
341.6active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-570 | Heritage - Wake 500 kV | 500 | 100 | Solar | Active | Dec 2028 |
| AG2-069 | Heritage - Wake 500 kV | 500 | 90 | Solar | Active | Dec 2029 |
| C01-1731 | Heritage - Wake 500 kV | 500 | 90 | Solar | Withdrawn | Sep 2030 |
| AG2-068 | Heritage - Wake 500 kV | 500 | 60 | Solar | Active | Dec 2029 |
| AG2-369 | Heritage - Wake 500 kV | 500 | 51.6 | Solar | Active | Dec 2030 |
| AG2-571 | Heritage - Wake 500 kV | 500 | 40 | Battery | Active | Dec 2028 |
| AG2-067 | Heritage - Wake 500 kV | 500 | 30 | Solar | Withdrawn | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Brunswick County, VA
- Carson-Wake: 1 active, 1,376 MW of 3 filed
- Unity - Rawlings: 1 active, 200 MW of 2 filed
- Rawlings - Unity: 1 active, 180 MW of 3 filed
- Brunswick: 4 active, 153.8 MW of 6 filed
- Heritage: 3 active, 109 MW of 5 filed
- Shackleford: 2 active, 12.2 MW of 3 filed
- Lawrenceville: 1 active, 11 MW of 3 filed
- Rawlings-Clover: none active of 6 filed
- Danieltown DP–Brunswick: none active of 2 filed
Other PJM queue substations in Halifax County, NC
- Dawson-South Justice: 3 active, 90.4 MW of 5 filed
- Hornertown-Hathaway: 2 active, 60.6 MW of 2 filed
- Cox-Whitakers: 1 active, 55.4 MW of 3 filed
- Hornertown-Whitakers: 2 active, 50 MW of 2 filed
- Hornertown: none active of 5 filed
Other PJM queue substations in Greensville County, VA
- Heritage-Carson: 1 active, 1,630 MW of 2 filed
- Carson-Rogers Road: 1 active, 207.2 MW of 2 filed
- Rogers Road - Carson: 1 active, 85 MW of 3 filed
- Carson-Rogers Rd: 1 active, 67.7 MW of 5 filed
- Rogers Road: 2 active, 67 MW of 5 filed
- Clubhouse-Lakeview: 1 active, 67 MW of 3 filed
- Brink: 1 active, 44 MW of 2 filed
- Emporia-Trego: 1 active, 42 MW of 3 filed
- Brink-Trego: 3 active, 40.4 MW of 3 filed
- Fields: 2 active, 17 MW of 3 filed
- Clubhouse- Purdy: none active of 6 filed
- Clubhouse: none active of 3 filed
- Carson – Rogers Road: none active of 2 filed
- Clubhouse-Freeman: none active of 2 filed
Site Scanner