Heritage - Wake substation interconnection queue

5 active projects totalling 341.6 MW in the PJM queue, plus 2 with terminal status (shown greyed).

5active projects
341.6active MW
7total filed
Queue IDProjectkVMWResourceStatus
AG2-570 Heritage - Wake 500 kV 500 100 Solar Active
AG2-069 Heritage - Wake 500 kV 500 90 Solar Active
C01-1731 Heritage - Wake 500 kV 500 90 Solar Withdrawn
AG2-068 Heritage - Wake 500 kV 500 60 Solar Active
AG2-369 Heritage - Wake 500 kV 500 51.6 Solar Active
AG2-571 Heritage - Wake 500 kV 500 40 Battery Active
AG2-067 Heritage - Wake 500 kV 500 30 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.