Lawrenceville substation interconnection queue
1 active project totalling 11 MW in the PJM queue, plus 2 with terminal status (shown greyed).
1active projects
11active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| Q70 | Brunswick | 34.5 | 11 | Gas | In Service |
| O61 | Lawrenceville 34.5kV | 34.5 | 8 | Gas | Withdrawn |
| X2-061 | Lawrenceville 34.5kV | 34.5 | 4 | Gas | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.