Lawrenceville substation interconnection queue
1 active project totaling 11 MW in the PJM queue, plus 2 with terminal status (shown grayed).
3 PJM queue filings name Lawrenceville as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Jan 2007 to Jun 2012 (3 filings).
1active projects
11active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| Q70 | Brunswick | 34.5 | 11 | Gas | In Service | Nov 2007 |
| O61 | Lawrenceville 34.5kV | 34.5 | 8 | Gas | Withdrawn | Jan 2007 |
| X2-061 | Lawrenceville 34.5kV | 34.5 | 4 | Gas | Withdrawn | Jun 2012 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in King and Queen County, VA
- Harmony Village-Shackleford: 9 active, 146.6 MW of 11 filed
- Shackleford: 2 active, 12.2 MW of 3 filed
- Shacklefords: 2 active, 10.2 MW of 2 filed
- St. Johns DP-REC: none active of 2 filed
Other PJM queue substations in Brunswick County, VA
- Carson-Wake: 1 active, 1,376 MW of 3 filed
- Heritage - Wake: 5 active, 341.6 MW of 7 filed
- Unity - Rawlings: 1 active, 200 MW of 2 filed
- Rawlings - Unity: 1 active, 180 MW of 3 filed
- Brunswick: 4 active, 153.8 MW of 6 filed
- Heritage: 3 active, 109 MW of 5 filed
- Shackleford: 2 active, 12.2 MW of 3 filed
- Rawlings-Clover: none active of 6 filed
- Danieltown DP–Brunswick: none active of 2 filed