Dawson-South Justice substation interconnection queue
3 active projects totaling 90.4 MW in the PJM queue, plus 2 with terminal status (shown grayed).
5 PJM queue filings name Dawson-South Justice as the point of interconnection, all in NC.
Target commercial operation dates as filed run from Jun 2019 to Nov 2025 (5 filings).
3active projects
90.4active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI2-301 | Dawson-South Justice 115kV | 115 | 45.1 | Solar | Withdrawn | Jun 2025 |
| AC2-084 | American Beech Solar | 115 | 40.2 | Solar | In Service | Nov 2025 |
| AC1-098 | American Beech Solar | 115 | 37.6 | Solar | In Service | Nov 2025 |
| AC2-083 | Dawson-South Justice 115kV | 115 | 13.4 | Solar | Withdrawn | Jun 2019 |
| AC1-099 | American Beech Solar | 115 | 12.6 | Solar | In Service | Nov 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Halifax County, NC
- Heritage - Wake: 5 active, 341.6 MW of 7 filed
- Hornertown-Hathaway: 2 active, 60.6 MW of 2 filed
- Cox-Whitakers: 1 active, 55.4 MW of 3 filed
- Hornertown-Whitakers: 2 active, 50 MW of 2 filed
- Hornertown: none active of 5 filed
Other PJM queue substations in Alamance County, NC
No other substation in Alamance County, NC is named as a point of interconnection in the PJM queue.