Emporia-Trego substation interconnection queue

1 active project totaling 42 MW in the PJM queue, plus 2 with terminal status (shown grayed).

3 PJM queue filings name Emporia-Trego as the point of interconnection, all in Greensville County, VA.

Target commercial operation dates as filed run from Dec 2017 to Feb 2023 (3 filings).

1active projects
42active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AB2-174 Greensville County Solar Project 115 42 Solar In Service Dec 2020
AI2-391 Emporia-Trego 115kV 115 13 Solar Withdrawn Feb 2023
AB1-070 Emporia-Trego 115kV 115 0 Solar Withdrawn Dec 2017

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Greensville County, VA

All 58 PJM queue filings in Greensville County, VA.