Substation Scout

Emporia-Trego substation interconnection queue

1 active project totalling 42 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
42active MW
3total filed
Queue IDProjectkVMWResourceStatus
AB2-174 Greensville County Solar Project 115 42 Solar In Service
AI2-391 Emporia-Trego 115kV 115 13 Solar Withdrawn
AB1-070 Emporia-Trego 115kV 115 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.