Halifax, NC interconnection queue

8 active projects totalling 355.8 MW in the PJM queue, plus 14 with terminal status (shown greyed).

8active projects
355.8active MW
22total filed
Queue IDProjectkVMWResourceStatus
C01-2145 South Justice - Dawsons Crossroads DP 115 kV 115 100 Hybrid Active
C01-1731 Heritage - Wake 500 kV 500 90 Solar Withdrawn
AI1-113 New Halifax - Dawson 115 kV 115 74.9 Hybrid Withdrawn
AD1-029 Scotland Neck-South Justice 115 kV 115 66.3 Hybrid Withdrawn
AC1-208 Halifax County Solar 115 55.4 Solar Under Construction
C01-1464 Bynums Bridge 115 kV 115 49.6 Battery Active
AI2-301 Dawson-South Justice 115kV 115 45.1 Solar Withdrawn
AA2-057 Chestnut Solar 115 44.7 Solar In Service
AC2-084 American Beech Solar 115 40.2 Solar In Service
AD1-056 Sweetleaf Solar 230 38.9 Solar Engineering and Procurement
AF2-219 Not reported n/r 38.7 Solar Withdrawn
AD1-057 Sweetleaf Solar 230 21.7 Solar Engineering and Procurement
AI2-295 Cox-Whitakers 115kV 115 20.6 Solar Withdrawn
AA2-055 Hornertown 34.5kV 34.5 14 Solar Withdrawn
AA2-056 Hornertown 34.5kV 34.5 14 Solar Withdrawn
AA2-068 N301 Solar 115 13.7 Solar Withdrawn
AA2-105 Hornertown 34.5kV 34.5 13.6 Solar Withdrawn
AC2-083 Dawson-South Justice 115kV 115 13.4 Solar Withdrawn
AA2-113 Hornertown 34.5kV 34.5 10.9 Solar Withdrawn
AB1-053 Hornertown 34.5kV 34.5 6.4 Solar Withdrawn
AA2-165 Chestnut Solar 115 5.3 Solar In Service
AG1-159 Cox-Whitakers 115 kV 115 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.