Substation Scout

Fields substation interconnection queue

2 active projects totalling 17 MW in the PJM queue, plus 1 with terminal status (shown greyed).

2active projects
17active MW
3total filed
Queue IDProjectkVMWResourceStatus
AF2-299 Jarratt Energy Facility 2 34.5 10.8 Solar Withdrawn
AF1-292 Jarratt Solar 34.5 8.9 Solar Under Construction
AG1-532 Fields 2 34.5 8.1 Solar Under Construction

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.