Substation Scout

Frostburg 138 kV

PJM queue ID AE2-289

Frostburg 138 kV (AE2-289) is listed in the PJM interconnection queue as a 11.8 MW wind project in Allegany County, MD. The filing names Frostburg as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2021.

Queue IDAE2-289
Project nameFrostburg 138 kV
Status (as published)Active
SubstationFrostburg
Point of interconnectionFrostburg 138 kV
CountyAllegany
StateMD
Voltage138 kV
Capacity11.8 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2021-12-31
Source datasetserial

Same substation and county

Frostburg substation: 6 requests in the PJM queue, 3 active totaling 19.6 MW.

Queue IDProjectMWResourceStatus
Z2-013Twin Ridges Wind Farm4.9WindIn Service
AB2-038Frostburg 138kV2.9WindIn Service
AI2-490Frostburg 138 kV31.9WindWithdrawn
AE2-030Frostburg 138kV7.6SolarWithdrawn
AB2-041Mason Dixon Wind Farm3.7WindWithdrawn

Allegany, MD: 23 requests in the PJM queue, 6 active totaling 190.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy80
MW capacity11.76
MFO80

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.