Substation Scout

Rockwood substation interconnection queue

1 active project totalling 8 MW in the PJM queue, plus 4 with terminal status (shown greyed).

1active projects
8active MW
5total filed
Queue IDProjectkVMWResourceStatus
L13 Casselman WF1 n/r 8 Wind In Service
AG1-205 Rockwood 23 kV 23 6.5 Solar Withdrawn
AG2-434 Rockwood 23 kV 23 6 Solar Withdrawn
AH2-359 Rockwood 23kV 23 3.2 Solar Withdrawn
L11 Rockwood 25 kV 25 2 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.