Substation Scout

Somerset-Allegheny substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
AG1-356 Somerset-Allegheny 115 kV 115 21.6 Solar Withdrawn
M08 Stonycreek n/r 20 Wind Withdrawn
O17 Stoney Creek WF 115 13 Wind Withdrawn
AA1-046 Kimberly Run Wind Farm 115 10.4 Wind Withdrawn
I04 Stonycreek 115 9 Wind Withdrawn
K12 Somerset-Allegheny 115kV 115 2.7 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.