Somerset-Allegheny substation interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).
0active projects
0active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG1-356 | Somerset-Allegheny 115 kV | 115 | 21.6 | Solar | Withdrawn |
| M08 | Stonycreek | n/r | 20 | Wind | Withdrawn |
| O17 | Stoney Creek WF | 115 | 13 | Wind | Withdrawn |
| AA1-046 | Kimberly Run Wind Farm | 115 | 10.4 | Wind | Withdrawn |
| I04 | Stonycreek | 115 | 9 | Wind | Withdrawn |
| K12 | Somerset-Allegheny 115kV | 115 | 2.7 | Wind | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.