Frostburg 138kV
PJM queue ID AB2-038
Frostburg 138kV (AB2-038) is listed in the PJM interconnection queue as a 2.9 MW wind project in Allegany County, MD. The filing names Frostburg as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2020.
| Queue ID | AB2-038 |
|---|---|
| Project name | Frostburg 138kV |
| Status (as published) | In Service |
| Substation | Frostburg |
| Point of interconnection | Frostburg 138kV |
| County | Allegany |
| State | MD |
| Voltage | 138 kV |
| Capacity | 2.9 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2020-12-31 |
| Source dataset | serial |
Same substation and county
Frostburg substation: 6 requests in the PJM queue, 3 active totaling 19.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AE2-289 | Frostburg 138 kV | 11.8 | Wind | Active |
| Z2-013 | Twin Ridges Wind Farm | 4.9 | Wind | In Service |
| AI2-490 | Frostburg 138 kV | 31.9 | Wind | Withdrawn |
| AE2-030 | Frostburg 138kV | 7.6 | Solar | Withdrawn |
| AB2-041 | Mason Dixon Wind Farm | 3.7 | Wind | Withdrawn |
Allegany, MD: 23 requests in the PJM queue, 6 active totaling 190.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 0 |
| MW capacity | 2.9 |
| MFO | 139.4 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.