Scalp Level substation interconnection queue

1 active project totaling 6.3 MW in the PJM queue, plus 5 with terminal status (shown grayed).

6 PJM queue filings name Scalp Level as the point of interconnection, all in Somerset County, PA.

Target commercial operation dates as filed run from May 2003 to Oct 2025 (6 filings).

1active projects
6.3active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
I15 Scalp Level 115kV 115 9.9 Gas Withdrawn May 2003
AG1-241 Scalp Level 23 kV 23 6.5 Solar Withdrawn Dec 2022
AH2-360 Scalp Level 23 kV 23 6.5 Solar Withdrawn Dec 2024
AF1-218 Scalp Level 23 kV 23 6.3 Solar Withdrawn Dec 2020
AF2-221 Stony Creek Solar 22.9 6.3 Solar Suspended Oct 2025
AG1-033 Scalp Level 23 kV 23 3.2 Solar Withdrawn Dec 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Somerset County, PA

All 107 PJM queue filings in Somerset County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.