Scalp Level substation interconnection queue

1 active project totalling 6.3 MW in the PJM queue, plus 5 with terminal status (shown greyed).

1active projects
6.3active MW
6total filed
Queue IDProjectkVMWResourceStatus
I15 Scalp Level 115kV 115 9.9 Gas Withdrawn
AG1-241 Scalp Level 23 kV 23 6.5 Solar Withdrawn
AH2-360 Scalp Level 23 kV 23 6.5 Solar Withdrawn
AF1-218 Scalp Level 23 kV 23 6.3 Solar Withdrawn
AF2-221 Stony Creek Solar 22.9 6.3 Solar Suspended
AG1-033 Scalp Level 23 kV 23 3.2 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.