Substation Scout

Central City West substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
F09 Central City West 23kV 23 9 Gas Withdrawn
AG2-651 Central City West 23 kV 23 6.2 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.